Project data


Organisations concerned:

Investor:

Municipality of Budapest

Project management:

Enviroduna Project Management Ltd.

Contribution organisation:

Ministry of National Development

Partner organisations:

Conduit Company of Budapest

Public Transport Company of Budapest

 

Beneficiary:

Municipality of Budapest, address: 1052 Budapest, Városház str. 9-11.

Name of project:

Budapest Complex Integrated Sewage Disposal project

KEOP -1.2.0./09-11-2011-0056

Project summary:

Partnership of Budapest Capital Municipality and Budaörs Municipality realizes the Budapest Complex Integrated Sewage Disposal Project in the framework of New Széchenyi Plan Environment and Energy Operative Programme (KEOP).

The investment involves the construction works of the sewage system of areas with no sewage, the construction of collectors among treatment plants and the construction of main collector ditributing wastewaters from south-buda and Budaörs to the Central Wastewater Treatment Plant. The new system enables the sewerage rate in Budapest to reach the 99.9 % meeting the EU and national requirements.

Significant life quality improvement of more than 41 000 persons  in the capital is taking place by construction of appr. 240 km long sewer  and connection to the main public utility system of more than 14 000 houses.

Awarded assistance

27 598 386 311 HUF

Rate of assistance:

83 %

Date of decision:

12th of February  2013.

Planned completion:

31st of July 2015.

 

The total cost of the investment is 34,1 billion HUF . The project has been supported by the European Union, co-financed by the Cohesion Fund. The amount of co-finance is 27,6 billion HUF. 